Enquire

qConstruction Update

08.10.2021

Upcoming works for the next month include:

  • Level 2 suspended slab works nearing completion
  • Level 3 suspended slab works complete advanced;
  • Level 4 typical upper level on north suspended slab complete;
  • Level 5 typical upper level on north suspended slab works commenced;
  • Vertical structural elements progressing with slabs
  • Internal walls and linings to levels LG – 3 northern end advanced;
  • Services reticulation advancing with internal walls and linings; and
  • Services install to lower ground carpark areas progressing.

20.07.21

  • Level 2 suspended slab works advanced
  • Vertical structural elements progressing with slabs
  • Internal walls and linings to ground level apartments commenced
  • Services reticulation advancing with structure
  • Services to retail/commercial parking areas commenced

10.05.21

Upcoming works for the next month include:

  • Ground level suspended slab and loading dock slab on ground complete;
  • Townhouse ground level and suspended slabs complete;
  • Mezzanine slabs complete;
  • Level 1 suspended slab progressing;
  • Vertical structural elements and services penetrations completed as slabs progress.

25.03.2021

22.02.2021

More concrete slabs are going down! Basement is being completed

10.02.2021 Bulk earthworks almost complete

13.01.2021 Concrete poured!

BGC have poured 300m3 of concrete last week which was pad and raft footings. This week we have poured approximately 160m3 so far and have a further pour of 140m3 on Thursday. This is pad and raft footings as well as some columns.

20.12.2020 Cranes are up!

20.11.2020 Display Suite Open

Display Suite has been moved and open for viewing this weekend 2:30pm to 3:30pm.

13.11.2020 Excavation is Underway!

Bulk excavation has begun and the Display Suite will be moved next week to make way for site works.

29.10.2020 Construction Commenced!

Construction has commenced at Shenton Quarter! The turning of soil event occurred with the whole team – Iris Residential, Primewest, BGC Construction, DevelopmentWA, Cameron Chisholm Nicol and Minister for Land Ben Wyatt to mark this exciting occasion!

Sales suite open Saturday and Sunday 2:30pm to 3:30pm